A leak inside a manufactured home does not run to the ground. It soaks the particleboard floor, drips into the belly and sits in the insulation, so the damage is often bigger below the floor than above it.
Checking the belly
- Belly material pulled back at the wet spot
- Wet insulation removed and bagged
- Joists and the underside of the floor metered
Meters confirm which sections of particleboard are wet, and a small opening in the belly shows what insulation is holding. A larger section is opened only if the water has spread beyond the first spot.
Floors that swell
Particleboard swells when it is wet and rarely goes back, so soft or raised areas are usually replaced after drying. Flooring above is lifted so air can reach the board, and the subfloor is read before anything is covered.
Drying from below the floor
Air movers and a dehumidifier, as in structural drying, are set to push dry air through the belly, and the opening is patched once the joists read dry. When the water came from sewage, the sewage backup protocol applies and more of the belly may be replaced.
Photos before and after opening the belly, plus daily readings, give the adjuster a complete file.